RST·DATA

Launch & orbit verification

Commissioning the observatory

The flight plan runs 110 days from liftoff on 30 Aug 2026 to science operations: unfold, cool, focus, check out. NASA expects science operations to begin by early 2027.

Confirmed so far

10 milestones NASA has reported, newest first. Everything below this panel is the modeled plan.

  1. 22 Sept 2026

    L+23d

    Coronagraph's first observation

    The Coronagraph Instrument saw starlight for the first time: a faint star in the Large Magellanic Cloud, then a crowded field there showing many stars in a single image. Fine guidance was tested with the instrument on 22 and 27 Sep. NASA ↗

  2. 21 Sept 2026

    L+22d

    Fine guidance verified

    A week of tests (15–21 Sep) showed the observatory can hold its pointing to better than 1/100,000 of a degree: for half an hour at a time for Wide Field Instrument exposures, eight hours for the Coronagraph. NASA ↗

  3. 17 Sept 2026

    L+18d

    Ground stations ready

    The last of three downlink tests passed: JAXA's Misasa station in Japan (7 Sep, up to 500 Mbit/s), the Near Space Network antennas at White Sands (8–11 Sep) and ESA's New Norcia station in Western Australia (17 Sep). Roman will send down about 1.4 terabytes a day, the most of any NASA astrophysics mission. NASA ↗

  4. 15 Sept 2026

    L+16d

    First photons

    A test exposure with the detector array still in its stowed launch position, far from focus: a field of out-of-focus stars, each spread over thousands of pixels. The baseline for aligning and focusing the telescope. Science images are expected by early 2027. NASA ↗

  5. 11 Sept 2026

    L+12d

    Wide Field Instrument activated

    After ten days of decontamination at −65 °C, the heater was switched off, the WFI cooled to −143 °C and all 18 detectors were powered. Calibration lamp that night, element wheel on the 12th, focus mechanism on the 13th. NASA ↗

  6. 01 Sept 2026, 12:22 UTC

    L+2.0d

    Coronagraph powered on

    Power-on complete after 55 minutes. A 30-day decontamination follows before its mechanisms are exercised. NASA ↗

  7. 01 Sept 2026, 10:05 UTC

    L+1.9d

    Aperture cover deployed

    Three spring booms raised the visor-like sunshade over eight minutes. The telescope is open to the sky. NASA ↗

  8. 31 Aug 2026, 18:03 UTC

    L+1.3d

    High-gain antenna deployed

    The 1.7 m dual-band dish, four minutes to deploy. NASA ↗

  9. 31 Aug 2026, 16:02 UTC

    L+1.2d

    First mid-course correction

    A three-minute burn, executed with better than 99% accuracy and less propellant than budgeted. NASA later put the fuel margin at 22+ years of operations. NASA ↗

  10. 30 Aug 2026, 11:26 UTC

    L+0.0d

    Liftoff

    Falcon Heavy from LC-39A. Separation from the second stage at 11:57 UTC; solar array deployed within the hour. NASA ↗

Get an email when Roman's first science images are released

NASA expects them by early 2027. One email then, one when survey data starts flowing. Nothing else.

Sequence overview

12 activities, launch through first science

Ascent & Separation
Initial Acquisition
Structural Deployments
Trajectory Correction 1
Outgassing & Cooldown
Trajectory Correction 2
L2 Orbit Insertion
Telescope Alignment & Focus
Wide Field Instrument Checkout
Coronagraph Technology Demo
First Light & Early Release
Science Operations
30 Aug 202629 Sept 202629 Oct 202628 Nov 202628 Dec 2026

Every activity, in order

  1. Ascent & Separation

    Launch Vehicle · L+0d → L+1h

    scheduled

    Falcon Heavy lofts the observatory onto a trans-L2 injection trajectory. Separation occurs roughly 40 minutes after liftoff.

    Planned steps: Fairing separation · Second-stage cutoff · Observatory separation · Initial tip-off rates damped

    Planned window 30 Aug 2026 → 30 Aug 2026

  2. Initial Acquisition

    Spacecraft Bus · L+1h → L+1d

    scheduled

    Solar array deploys and the observatory establishes a power-positive, thermally safe attitude. First contact through the Deep Space Network confirms a healthy bus.

    • Liftoff · 30 Aug 2026 · NASA ↗
    • Ground stations ready · 17 Sept 2026 · NASA ↗

    Planned steps: Solar array deployed and latched · Sun-pointed safe attitude · First DSN acquisition of signal · Bus telemetry nominal

    Planned window 30 Aug 2026 → 31 Aug 2026

  3. Structural Deployments

    Mechanisms · L+1d → L+5d

    scheduled

    The high-gain antenna, the deployable aperture cover and the solar-array sunshade move to their flight configurations. Each release is commanded and verified individually.

    • High-gain antenna deployed · 31 Aug 2026 · NASA ↗
    • Aperture cover deployed · 01 Sept 2026 · NASA ↗

    Planned steps: High-gain antenna deployed · Deployable aperture cover open · Sunshade fully extended · Mechanism telemetry within limits

    Planned window 31 Aug 2026 → 04 Sept 2026

  4. Trajectory Correction 1

    Flight Dynamics · L+1d → L+1d

    scheduled

    The first and largest correction burn removes launch-vehicle injection error. It must fire early — a trans-L2 trajectory is deliberately biased short so it can never be aimed at the observatory's own sunshade.

    • First mid-course correction · 31 Aug 2026 · NASA ↗

    Planned steps: Burn attitude achieved · TCM-1 executed · Post-burn orbit determination

    Planned window 31 Aug 2026 → 31 Aug 2026

  5. Outgassing & Cooldown

    Thermal · L+2d → L+45d

    scheduled

    Trapped water and volatiles bake off the optics while passive radiators pull the Wide Field Instrument's detectors toward their 95 K operating point. This is the long pole of commissioning and cannot be rushed.

    • Wide Field Instrument activated · 11 Sept 2026 · NASA ↗

    Planned steps: Decontamination heaters cycled · Optical bench below 200 K · WFI focal plane at 95 K · Detector dark current within spec

    Planned window 01 Sept 2026 → 14 Oct 2026

  6. Trajectory Correction 2

    Flight Dynamics · L+4d → L+7d

    scheduled

    A small mid-course cleanup burn, flown only if needed, refines the approach so that the insertion maneuver at L2 stays inside its propellant budget.

    Planned steps: TCM-2 executed · Approach corridor confirmed

    Planned window 03 Sept 2026 → 06 Sept 2026

  7. L2 Orbit Insertion

    Flight Dynamics · L+100d → L+101d

    scheduled

    A modest burn at the edge of the Earth–Sun L2 region captures the observatory into a wide halo orbit roughly 1.5 million km from Earth. The halo is unstable by design, so it is maintained with small station-keeping burns every few weeks.

    Planned steps: Insertion burn executed · Halo orbit confirmed by ranging · Station-keeping cadence established

    Planned window 08 Dec 2026 → 09 Dec 2026

  8. Telescope Alignment & Focus

    Optical Telescope Assembly · L+45d → L+72d

    scheduled

    Wavefront sensing on a star field drives the secondary mirror actuators until the point-spread function converges on its diffraction-limited shape across the full 0.28 square-degree field.

    Planned steps: Fine guidance sensor locked on a star · Coarse focus sweep · Wavefront error below 90 nm RMS · Field-dependent aberrations mapped

    Planned window 14 Oct 2026 → 10 Nov 2026

  9. Wide Field Instrument Checkout

    WFI · L+12d → L+100d

    scheduled

    All eighteen H4RG detectors are exercised through every element of the filter wheel. Flat fields, darks, gain and linearity are measured to build the first flight calibration reference files. Activated 11 Sep 2026, during cooldown.

    • Wide Field Instrument activated · 11 Sept 2026 · NASA ↗
    • First photons · 15 Sept 2026 · NASA ↗
    • Fine guidance verified · 21 Sept 2026 · NASA ↗

    Planned steps: All 18 SCAs reading out · First photons on the focal plane · Filter wheel full sweep · Photometric zero points established · Grism and prism dispersion solved

    Planned window 11 Sept 2026 → 08 Dec 2026

  10. Coronagraph Technology Demo

    CGI · L+75d → L+105d

    scheduled

    The Coronagraph Instrument's deformable mirrors run their dark-hole digging algorithm, suppressing starlight to demonstrate the contrast future missions will need to image Earth-like planets.

    • Coronagraph powered on · 01 Sept 2026 · NASA ↗
    • Coronagraph's first observation · 22 Sept 2026 · NASA ↗

    Planned steps: Deformable mirrors responsive · Dark hole convergence · Contrast floor measured

    Planned window 13 Nov 2026 → 13 Dec 2026

  11. First Light & Early Release

    Science Operations · L+100d → L+110d

    scheduled

    The first science-grade images are taken, processed and released publicly — the observatory's formal introduction.

    Planned steps: First-light exposure · Pipeline end-to-end run · Early Release Observations published

    Planned window 08 Dec 2026 → 18 Dec 2026

  12. Science Operations

    Science Operations · L+110d → L+1825d

    scheduled

    The Core Community Surveys begin. Data flows to the archive continuously and becomes public immediately — there is no proprietary period on Roman survey data.

    Planned steps: High Latitude Wide Area Survey underway · Galactic Bulge Time Domain Survey underway · High Latitude Time Domain Survey underway

    Planned window 18 Dec 2026 → 29 Aug 2031